Air Management Programs
Department of Natural Resources
February 2004
Report Highlights
The Department of Natural Resources (DNR) administers state and
federal air management programs that regulate the emission of pollutants
that have been linked to health problems in humans, as well as to
smog and acid rain. As part of this responsibility, DNR is required to
ensure that the 2,219 utilities, factories, and other stationary facilities it
regulates are complying with the terms of their permits, and to monitor
air quality throughout Wisconsin.
Representatives of regulated facilities contend that complying with
Wisconsin’s air pollution regulations is onerous and expensive, while
representatives of environmental groups believe too little is being done
to ensure compliance with state and federal air pollution laws. In
response to concerns about the time DNR takes to issue permits, the
fees regulated facilities are charged, the extent to which the State
regulates air pollution beyond federal requirements, and DNR’s approach
to regulating sources of air pollutionand at the request of the
Joint Legislative Audit Committeewe analyzed:
permit backlogs, including the amount of time taken to issue operation
and construction permits;
the amount of time other states require to issue operation and
construction permits;
the equitableness of fees assessed to regulated facilities emitting
varying amounts of pollutants;
the extent to which Wisconsin has expanded upon regulatory
requirements prescribed by federal law;
air quality monitoring efforts by DNR staff; and
compliance and enforcement efforts.
Operation Permits
As of June 30, 2003, DNR had
issued operation permits to
50.8 percent of the 2,219 facilities
that had applied for them,
including:
64.4 percent of federally
required “major” permits,
which have the highest potential
air pollution emissions;
73.5 percent of federally
required “synthetic minor”
permits, which have lower
potential air pollution emissions;
and
8.2 percent of state-required
“minor” permits, which have
the lowest potential air pollution
emissions.
In total, 1,128 permits were issued but 1,091 were backlogged.
Under the federal Clean Air Act,
Wisconsin was required to issue
operation permits to all major
facilities by March 1998. However,
Wisconsin issued only 64.4 percent
of its major operation permits by
June 30, 2003, the lowest percentage
in the Midwest. By comparison,
80.9 percent of major permits
had been issued nationally.
2003 Wisconsin Act 118, which
took effect February 6, 2004,
streamlines DNR’s operation
permit program and may help to
address the permit backlog. DNR
has also made several revisions
to its plan for issuing operation
permits and now anticipates
issuing all federally required
major permits by January 2005.
No deadlines have been established
for issuing either synthetic minor
operation permits or minor
operation permits. We make
several recommendations to
further streamline the operation
permitting process.
Construction Permits
Wisconsin statutes and administrative
rules require DNR to issue
permits for new construction
and facility modifications within
specified time limits.
DNR does not adequately track the
time it takes to issue permits, but
we found that, based on a random
sample of 88 construction permit
applications, DNR met statutory
deadlines for 86.4 percent of
construction permits issued.
However, 29.2 percent of all construction
permits pending as of
June 30, 2003, had been backlogged
for at least two years.
DNR officials indicate that construction
permits can become
backlogged because some projects
will be undertaken in the future,
and permits for electrical generating
facilities require approval from
other regulatory bodies.
Because DNR has substantial
flexibility in determining when an
application is deemed complete
and the statutory clock begins,
we analyzed the time taken to
issue permits from the dates applications
were received. For the
88 permits in our sample, the
median time was 103.5 days,
including 52 permits issued within
120 days and 9 that took longer
than one year.
2003 Wisconsin Act 118 reduces
the time DNR is allowed for issuing
construction permits. We make
several recommendations to further
streamline the construction
permitting process.
Additional State
Requirements
Wisconsin has expanded on federal
air management requirements in
two primary areas. First, Wisconsin
regulates 293 more hazardous air
pollutants than required by federal
law. Of these, 94 were reported
emitted by Wisconsin facilities
in 2002. Three of five other
midwestern states also exceed
federal requirements for regulating
hazardous air pollutants.
Second, Wisconsin facilities
with potential emissions below
federal requirements are generally
required to obtain state-mandated
minor operation permits. As of
June 30, 2003, 687 facilities had
applied for minor operation permits,
but only 56 of these permits
had been issued.
Enforcement Efforts
The number of facilities DNR
inspects annually has generally
declined over time, from 470 in
fiscal year (FY) 1994-95 to 276 in
FY 2002-03. DNR’s records indicate
that 15.0 percent of facilities
have never been inspected.
In addition, DNR has failed to
follow its own policies regarding
enforcement against facilities that
apply for construction permits
after work is already complete, or
against facilities that do not submit
timely compliance certifications.
We also found that DNR does not
consistently follow federal policy in
taking enforcement actions for
high-priority violations. We make
several recommendations to improve
DNR’s enforcement efforts.
Program Management
We identified a pattern of significant
deficiencies in DNR program
management, including:
failing to identify 71 facilities
that were required to apply for
operation permits although
DNR records indicate they did
not, and failing to have documentation
for why an additional
175 facilities may be
exempt from permitting;
failing to issue 113 operation
permits even though they had
already completed a public
comment period and could
have been issued, including 106
that could have been issued
before June 30, 2002;
failing to ensure that 49 facilities
applied for renewal operation
permits when required; and
having no explanation for why
232 facilities have not reported
emissions or paid emission fees,
billing 11 facilities approximately
$21,000 when they
should not have been billed,
and failing to bill 13 other
facilities approximately
$27,000.
In addition to the program and
policy changes that recently took
effect under 2003 Wisconsin
Act 118, a number of proposed
changes in federal law could also
significantly affect the State’s air
management programs. Regardless
of changes already enacted at the
state level and additional changes
that may result from efforts to
modify federal requirements, DNR
program management will need to
be improved if Wisconsin’s air
management goals are to be
accomplished.